Construction at Coldstream Elementary School

Completion of Parking Lot

 
First Bus
First Bus through completed parking lot.
parking lot
Coldstream Elementary Construction Wrapping up - April 27, 2011

“The Coldstream Elementary school replacement project is almost completed. The parking lot and bus loop are scheduled to be completed for the last week of April 2011.

See the layout of the parking area and traffic flow diagram.

The new school construction started in July 2009 and was ready for the students and staff move in on November 2010. This is a one storey school with a daylight basement and has floor area of 3250m2. There are 15 classrooms, two kindergarten rooms, kitchen, gymnasium, library, multipurpose space and the administration areas.

This school has a geothermal system and lighting control system to reduce energy consumption and will provide operating cost savings. The design has been to a LEED Gold standard (Leadership in Energy and Environmental Design).

The exterior will have a full size sports field, paved basketball and play area, and two playground equipment zones.”

More pictures
Codlstram
Coldstream school
Architect Rendition Landascape Site Plan Option 3 Exterior Elevations
School Plant Officials Association of B.C.
Loading
bootm
Home
I District I Schools I Students I Parents I Human Resources I International I Webmail I Contact the District
September 22, 2011
© School District No. 22 (Vernon) 2011

vLearn site
 
Take me to the home page